Model study: an illustrative feasibility analysis built on public data for Maricopa County, Arizona; not a client engagement.
Project summary
| Item | Modelled value |
|---|---|
| Asset | New single-site K-8 charter school building, 40,000 sq ft on a 10-acre parcel, design capacity 500 students |
| Owner and operator | Nonprofit charter holder (single charter, single site), authorized by the Arizona State Board for Charter Schools |
| Location | Town of Wickenburg, Maricopa County portion, Arizona (2025 town estimate 8,305 [1]; its own 2020 urban area, separate from the Phoenix--Mesa--Scottsdale urban area [2]) |
| Program | USDA Rural Development Community Facilities (CF) direct loan, 7 CFR part 1942 subpart A [3] |
| Total project cost | $18,839,893 ($37,680 per seat) |
| Loan structure | CF direct loan $16,939,893 (89.9%); 4.75% fixed (assumed market tier); 35-year term; interest-only Years 1 and 2, Year 1 interest capitalized; level P&I $1,026,635 from FY2031 |
| Equity | $1,900,000 (10.1%): land, start-up funds and cash from grants or philanthropy |
| Stabilized DSCR | 1.30x at 475 average daily membership (ADM) under the sponsor ramp; 0.80x under the conservative 320-ADM case |
| Returns (notional) | Unlevered IRR 5.3%; levered IRR 13.6%; equity multiple 2.53x; exit value $16.8M at an 8.0% cap rate |
| Break-even | 410 ADM for 1.00x (82% of capacity); 456 ADM for 1.20x (91%) |
| Determination | Not financeable as structured. Break-even needs about 17.5% of every K-8 student living in a six-ZIP trade area, and full design enrollment about 20%, the statewide charter share of public enrollment. A resized 330-seat first phase ($13.2M) on the same site reaches 1.40x at 320 ADM and is financeable under CF with conditions. |
The credit question
The credit decision on a charter school building is not really about the building. Arizona pays a charter school per student, almost entirely from state formula aid, and the authorizer can revoke or decline to renew the charter. A lender must be convinced of three things, in this order.
First, that the students exist. The modelled project assumes about 500 students in a town whose median age is 65.2 and where only 754 residents are under 18 [4]. Per-pupil funding is the only material revenue line, so if the trade area cannot supply the enrollment, nothing else in the file matters.
Second, that per-student revenue is what the model says. Arizona's formula layers a statutory base level, grade weights, a small-school weight that rises as enrollment falls, Group B weights, charter additional assistance and the Classroom Site Fund. Each layer moves debt capacity by tens of thousands of dollars.
Third, that the charter will still be in force when the loan is half paid. A CF direct loan can run 40 years [3]; an Arizona charter runs 15 years, renewable for 20-year periods, with reviews at five-year intervals [5]. The authorizer, not the lender, judges the performance on which repayment depends.
Location and county economy
Why Wickenburg, and why it is CF-eligible
CF essential community facility loans are not made to a city or town of more than 20,000 inhabitants in the most recent decennial census, and the facility must primarily serve rural areas [3]. Inside a county of 4.69 million people [1], the site must be under that limit and outside the Phoenix urban area. Two incorporated towns meet both tests.
| Test | Wickenburg (town) | Gila Bend (town) | Buckeye (city), for contrast |
|---|---|---|---|
| 2020 estimates base population | 7,514 [1] | 1,890 [1] | 91,498 [1] |
| July 2025 estimate | 8,305 [1] | 1,816 [1] | 125,445 [1] |
| Change, 2020 base to 2025 | +10.5% | -3.9% | +37.1% |
| 2020 urban area status | Own urban area "Wickenburg, AZ": 4,801 people, 2,826 housing units [2] | Not listed as an urban area [2] | Own urban areas "Buckeye, AZ" and "Buckeye North, AZ" [2]; city far above 20,000 |
| Phoenix--Mesa--Scottsdale urban area | Separate; that area holds 3,976,313 people [2] | Separate | n/a |
| CF population test (20,000 or less) | Passes | Passes | Fails |
Gila Bend passes eligibility but fails the market test outright: 1,816 residents, falling, cannot fill a 500-seat school. Wickenburg is more than four times its size and is growing. The growth is not where a reader would expect: the Maricopa County part of town slipped from 6,690 to 6,647 between the 2020 base and 2025, while the Yavapai County part doubled from 824 to 1,658 [1]. The modelled site is in the Maricopa portion; the Yavapai growth is inside the commuting shed. CF eligibility uses the decennial census count, which a lender must confirm, but every Census estimate for the town is below 10,000.
Households, age and income
| Measure | Wickenburg town | Wickenburg Unified District area | Maricopa County |
|---|---|---|---|
| Population | 8,059 | 20,080 | 4,559,748 |
| Median age | 65.2 | 65.1 | 37.6 |
| Under 18 | 754 (9.4%) | 2,498 (12.4%) | 1,024,257 (22.5%) |
| Enrolled in kindergarten to grade 8 | 486 | 1,316 | 509,346 |
| 65 and over | 51.3% | 50.2% | 16.3% |
| Persons per household | 1.81 | 2.06 | 2.59 |
| Median household income | $67,600 | $79,402 | $89,300 |
Source: ACS 2020 to 2024 5-year table-based summary file, tables B01003, B01002, B09001, B14001, B09020, B25010 and B19013 [4].
This table is the centre of the credit file. Wickenburg is a retirement community: half its residents are 65 or older and households average 1.8 people [4]. The families who live here are few. The ACS counts 486 town residents and 1,316 district-area residents enrolled in kindergarten through grade 8, in any type of school [4]. Small-area margins are wide, but the gap between those figures and 500 seats is not.
Income also sets the CF rate. The intermediate rate needs a service-area median household income below the poverty line or not more than 100% of Arizona's nonmetropolitan median, and the poverty line rate, for a facility that does not provide direct health care, also needs a project whose primary purpose is to meet health or sanitary standards [3], which a new school lacks. The town's $67,600 median is 84.5% of the $79,964 statewide median in the same ACS series [4]; whether it is at or below the RD nonmetropolitan figure is the open question. The model assumes the market tier.
County population
| Indicator | Latest | Earlier | Change |
|---|---|---|---|
| Maricopa County resident population | 4,689,558 (July 2025) [1] | 4,654,147 (July 2024) [1] | +0.8% |
| Maricopa County population, 2020 base to 2025 | 4,689,558 [1] | 4,425,302 (April 2020 base) [1] | +6.0% |
The county is large and still growing, slowly: 0.8% in the year to July 2025 [1]. It matters to this asset indirectly. It sets the teacher labour market, and it drives the residential growth that would eventually reach Wickenburg, which so far appears in the Yavapai part of town [1]. The school will depend on parent drop-off and a limited bus service; the model carries a transportation line.
Market analysis
Demand drivers
Charter demand in Arizona is real but no longer growing statewide. The Joint Legislative Budget Committee (JLBC) enrollment series shows the shift plainly.
| Fiscal year | District ADM | Charter ADM | Public subtotal | ESA enrollees | Charter share of public |
|---|---|---|---|---|---|
| FY2019 | 906,004 | 201,757 | 1,107,761 | 6,450 | 18.2% |
| FY2023 | 873,827 | 223,660 | 1,097,487 | 53,364 | 20.4% |
| FY2025 | 854,074 | 223,858 | 1,077,932 | 87,602 | 20.8% |
| FY2026 | 832,065 | 220,226 | 1,052,291 | 102,891 | 20.9% |
| FY2027 est. | 818,076 | 217,900 | 1,035,975 | 113,602 | 21.0% |
| FY2029 est. | 794,914 | 214,387 | 1,009,301 | 137,602 | 21.2% |
Source: JLBC FY2027 Appropriations Report, Department of Education, Table 3 [6]; shares computed.
Charters hold about a fifth of public enrollment, a fair precedent for a new charter in an unserved town. But public enrollment fell 2.4% from FY2025 to FY2026, and the budget assumes a further 1.6% decline in FY2027: 0.9% from demographic projections and 0.7% from students moving to the state's Empowerment Scholarship Account (ESA) program [6]. The Department of Education estimates that about 59% of students who newly enrolled in the universal ESA program in FY2026 were in a public school the year before [6]. The ESA competes for exactly the family a rural charter recruits, and its FY2027 budget, total awards of $1,215,678,900 for 113,602 enrollees or about $10,701 each [6], is close to modelled charter revenue per student.
The local driver is the absence of choice. The model assumes the project would be the town's only charter school, to be confirmed against the State Board for Charter Schools roster and Department of Education enrollment data. That is an advantage, but with no local precedent for how many families will switch.
Supply and the competitive set
The competition for a K-8 seat is the district's schools, ESA-funded private or home education, and schools in Surprise and Buckeye to the southeast. Wittmann and Morristown families are the most likely to use those alternatives already, so their assumed capture is lower.
Trade area and capture rates
The trade area is built from six ZIP Code Tabulation Areas (ZCTAs), grouped by distance from Wickenburg.
| ZCTA | Community | Population | Under 18 | Enrolled K to 8 | Median age | Median HH income |
|---|---|---|---|---|---|---|
| 85390 | Wickenburg (primary) | 10,298 | 1,318 | 794 | 64.5 | $68,591 |
| 85320 | Aguila (secondary) | 458 | 151 | 88 | 45.3 | $47,731 |
| 85342 | Morristown (secondary) | 1,823 | 362 | 178 | 49.4 | $55,917 |
| 85332 | Congress (secondary) | 1,577 | 132 | 132 | 69.1 | $56,165 |
| 85362 | Yarnell (secondary) | 638 | 44 | 28 | 67.3 | $47,609 |
| 85361 | Wittmann (tertiary) | 7,991 | 1,838 | 1,251 | 44.3 | $77,361 |
| Total | 22,785 | 3,845 | 2,471 |
Source: ACS 2020 to 2024 5-year table-based summary file, tables B01003, B09001, B14001, B01002 and B19013 [4]; "Enrolled K to 8" is kindergarten plus grades 1 to 4 plus grades 5 to 8.
Small-area ACS counts carry wide margins; Yarnell's 28 students in grades 5 to 8, for example, carry a margin of error of 47 [4]. The total should be read as roughly 2,500 K-8 students, plus or minus several hundred, and it covers every type of school, not only public ones.
The capture arithmetic is then straightforward.
| Enrollment target | Headcount needed (ADM ÷ 0.95) | Share of all 2,471 | Share excluding Wittmann (1,220) | Share of Wickenburg ZCTA only (794) |
|---|---|---|---|---|
| Design capacity, 500 headcount (475 ADM) | 500 | 20.2% | 41.0% | 63.0% |
| Break-even at 1.00x, 410 ADM | 432 | 17.5% | 35.4% | 54.4% |
| Conservative case, 320 ADM | 337 | 13.6% | 27.6% | 42.4% |
The statewide charter share of 20.9% of public enrollment in FY2026 [6] is a fair upper reference for capture across a whole trade area, because it already includes dense urban markets with many charter options. The 500-seat plan needs about that share of every K-8 student in all six ZIP areas, including Wittmann families who live closer to Surprise, in a town the model assumes has no charter school today. Without Wittmann the plan needs 41% of K-8 students in the remaining five ZIP areas, and break-even alone needs 35%. That is not a credible assumption for a lender to accept without evidence.
Forecast
The model carries two enrollment paths and one cross-check.
The sponsor ramp is the project as described: 300 ADM in FY2029 (the 2028 to 2029 school year), rising to 360, 410, 450 and 475 by FY2033 and holding there (95% of design capacity).
The cross-check applies capture by ring to the ACS counts: 30% of the Wickenburg ZCTA, 20% of the four secondary ZCTAs and 10% of Wittmann. That yields about 449 students, or about 426 ADM at a 95% ratio, which the sensitivity grid below puts at about 1.06x, short of 1.20x. Even those rates are generous for a new school with no local precedent; a lender would want them confirmed by intent-to-enroll forms.
The conservative case assumes the school stabilizes at 320 ADM instead, modelled as a ramp of 200, 240, 275, 300 and 320 ADM by FY2033. It stands for weaker capture or retention than the ring rates, and it is the case the resized first phase is built to survive. The difference between the paths is the whole credit story.
Site and technical
Site requirements. A 500-seat K-8 campus with a multipurpose room, play fields, parent queuing and bus loop needs about 10 acres, carried at an assumed $50,000 per acre. Water, sewer and power capacity must be confirmed before purchase; the $1.8 million site line includes off-site utility extensions.
Zoning. Arizona classifies a charter school the same as a school operated by a school district for zoning and for zoning, site plan and development fees, and a municipality or county must allow a charter school wherever its zoning cannot legally prohibit district schools [7]. Hearings and administrative reviews must be expedited, with a final determination within 30 days for an administrative review and within 90 days for a process that requires a public hearing [7]. Building codes, including life and safety codes, still apply [7]. That is a real schedule advantage. One limit binds: a charter school sponsored by the State Board for Charter Schools may not be located on the property of a school district unless the school district governing board grants this authority [5], so surplus district land is not a simple option.
Construction approach and cost benchmark. The model assumes a single-storey 40,000 sq ft building (80 sq ft per seat) at $285 per sq ft hard cost, plus $1.8 million of site work and a 6% contingency. The public benchmark is the School Facilities Division formula. Its statutory funding guidelines for FY2027 awards are 90 sq ft per K-6 student at $358.46 per sq ft and 100 sq ft per student in grades 7 and 8 at $378.44, increased by 5% for rural school districts [8]. At its January 2026 meeting the JLBC also approved a 4.8% adjustment in the cost per square foot, which first applies to projects beginning in FY2028 [8]. For 500 students in grades K to 8, the guidelines imply 46,111 sq ft and $17.59 million, or $381 per sq ft (computed). The modelled development cost excluding land, financing and start-up is $16.43 million, or $411 per sq ft on 13% less space: close to the state formula in total dollars.
Environmental and federal requirements. CF loans must comply with the environmental review rules in 7 CFR part 1970. Borrowers operate under title VI of the Civil Rights Act of 1964, and title IX of the Education Amendments of 1972 applies to education programs that receive Agency assistance. Loan funds must be kept in insured, interest-bearing accounts where possible [3].
Schedule.
| Phase (assumed) | Window | Credit relevance |
|---|---|---|
| Charter application, authorizer review and approval | FY2027 into FY2028 | No CF commitment without an approved charter |
| CF preapplication, eligibility, environmental review | Q1 to Q3 calendar 2027 | Credit-elsewhere certification [3] |
| Land purchase, design, zoning review | Q2 to Q3 2027 | Statutory 30-day and 90-day review deadlines [7] |
| Interim financing close, construction start | September 2027 | Interim commercial financing required for loans over $50,000 where available at reasonable rates [3] |
| Construction (11 months) | September 2027 to July 2028 | Without interim financing, advances are limited to 30-day needs [3] |
| CF permanent loan closes, school opens | August 2028 (FY2029) | Year 1 interest capitalized |
| Stabilization (sponsor ramp) | FY2033 | First full year at 475 ADM |
Development budget and sources and uses
Development budget
| Line item | Amount | Share | Per seat |
|---|---|---|---|
| Land (10 acres) | $500,000 | 2.7% | $1,000 |
| Site work and off-site utilities | $1,800,000 | 9.6% | $3,600 |
| Building hard cost (40,000 sq ft at $285) | $11,400,000 | 60.5% | $22,800 |
| Hard-cost contingency (6%) | $792,000 | 4.2% | $1,584 |
| Architecture and engineering (7.5% of hard) | $990,000 | 5.3% | $1,980 |
| Permits, plan review, testing (1.5% of hard) | $198,000 | 1.1% | $396 |
| FF&E and technology ($1,700 per seat) | $850,000 | 4.5% | $1,700 |
| Legal, title, appraisal, environmental, closing | $325,000 | 1.7% | $650 |
| Soft-cost contingency (3%) | $70,890 | 0.4% | $142 |
| Interim construction interest and fee | $709,358 | 3.8% | $1,419 |
| Capitalized CF interest, Year 1 | $804,645 | 4.3% | $1,609 |
| Initial operating expenses (start-up) | $400,000 | 2.1% | $800 |
| Total project cost | $18,839,893 | 100.0% | $37,680 |
All figures in this budget are model inputs and results. Interim interest assumes a 50% average draw over 11 months at 7.50% (the 7.00% bank prime rate of November 9, 2026 [9] plus 0.50%) and a 0.75% fee. Capitalized interest covers the first year's CF interest; loan funds may pay interest until the facility is self-supporting, for up to three years unless the National Office approves a longer period [3]. Initial operating expenses for a period ordinarily not exceeding one year are also an eligible loan purpose [3], but the model funds them from equity.
Sources and uses
| Sources | Amount | Share | Uses | Amount |
|---|---|---|---|---|
| USDA CF direct loan | $16,939,893 | 89.9% | Land | $500,000 |
| Sponsor equity: land | $500,000 | 2.7% | Hard costs and contingency | $13,992,000 |
| Sponsor equity: start-up funds | $400,000 | 2.1% | Soft costs and contingency | $2,433,890 |
| Sponsor equity: cash (grant or philanthropy) | $1,000,000 | 5.3% | Interim interest and fee | $709,358 |
| Capitalized CF interest | $804,645 | |||
| Initial operating expenses | $400,000 | |||
| Total | $18,839,893 | 100.0% | Total | $18,839,893 |
The 10.1% equity is a model choice, included because a lender wants evidence that a first-time sponsor can raise money. An applicant contributing funds must deposit them in its construction account on or before loan closing or the start of construction, whichever comes first [3].
Assumptions register
Every figure in the model that is not traced to a numbered source is an assumption. The material ones are below.
| Assumption | Value | Rationale |
|---|---|---|
| CF interest rate | 4.75% fixed, market tier | Assumption. The poverty line rate needs a health or sanitary purpose for a project that is not a health care facility [3]; the intermediate-tier income test is unconfirmed; the rate for the approval or closing quarter is to be confirmed |
| CF term and amortization | 35 years; 2 years interest-only | Inside the 40-year and useful-life cap [3]; shorter than 40 to reflect charter-term risk |
| Interim loan | Prime + 0.50% (7.50%), 0.75% fee | Prime 7.00% on November 9, 2026 [9]; assumed construction spread |
| Land | $50,000 per acre, 10 acres | Assumption; no comparable sales used |
| Hard cost | $285/sq ft, 40,000 sq ft | Assumption, cross-checked to the SFD formula [8] in total dollars |
| Funding inflation | 2.0% a year after FY2027 | Statute funds the lesser of 2% or the GDP price deflator; JLBC assumes GDP inflators of 3.7% for FY2028 and 2.8% for FY2029 [6] |
| Group B weights mix | SPED 12%, K-3 4/9, FRPL-eligible 30%, ELL 3% | Planning mix (assumption); weights from statute [10] |
| Small-school weight | Column for "small" (not "small isolated") districts | Statutory schedule [10]; the column that applies to a Wickenburg site is to be confirmed |
| ADM to headcount | 95% | Assumption; statute defines ADM as enrollment minus withdrawals, which include students absent for ten consecutive school days [11] |
| Federal categorical revenue | $520/student, 1% growth, fully offset by program spending | Assumption; Title I and IDEA allocations vary by student need |
| Other local revenue | $175/student, 2% growth | Assumption: fees, extracurricular and tax-credit donations |
| Teacher salary | $62,000 in FY2029, 2.5% growth; 25% benefits | Assumption, set below the FY2025 statewide district average of $65,613 [12] grown forward |
| Staffing ratios | 23 students per classroom teacher; 1 SPED or intervention teacher per 90; 1 aide per 80 | Assumption: planning ratios for a K-8 charter |
| Facility O&M | $7.50/sq ft, 3% growth; insurance $1.25/sq ft, 4% growth | Assumption: utilities, custodial, grounds and repairs for a new building in a hot climate |
| Capital replacement reserve | $0.75/sq ft, 2% growth, above the line | Assumption: lender convention for a new building |
| Exit cap rate | 8.0% | Assumption: special-use, single-tenant educational real estate |
| Property tax | None | Assumption: nonprofit-owned school treated as exempt; to be confirmed |
| Enrollment paths | Sponsor ramp to 475 ADM; conservative case to 320 ADM | Assumptions; tested against ACS K-8 counts [4] |
Revenue build and operating expenses
Per-student revenue build
Arizona charter funding starts from the district base support level formula in section 15-943, with three charter-specific differences: section 15-941 does not apply, the small-school weights apply to a holder of one charter, and charter additional assistance is added to the base support level [13]. Equalization assistance for a charter is paid as a single amount based on ADM, without categorical distinctions between maintenance and operations or capital [13].
| Component | Statutory or published FY2027 value | Modelled FY2029 value | Per student at 300 ADM | Per student at 475 ADM |
|---|---|---|---|---|
| Base level | $5,215.53 for fiscal year 2026-2027 [11] | $5,426.24 | ||
| Group A weight, K-8 | 1.158 standard; small-school schedule for counts under 600 [10] | 1.338 at 300 ADM; 1.2855 at 475 ADM | ||
| Group B weights (mix) | SPED 0.292, K-3 0.060, FRPL 0.022, ELL 0.115 [10] | 0.0718 combined | ||
| Base support level (base × (A + B)) | $7,650 | $7,365 | ||
| Charter additional assistance, K-8 | $2,174.54 [13] | $2,262.39 | $2,262 | $2,262 |
| Classroom Site Fund | $883 per weighted pupil [14] | $918.67 × 1.158 | $1,064 | $1,064 |
| Federal categorical (assumption) | $520 | $520 | $520 | |
| Other local (assumption) | $175 | $175 | $175 | |
| Total per student | $11,671 | $11,386 |
Modelled FY2029 values grow the FY2027 amounts by the assumed 2.0% a year; per-student figures are model results. The small-school weight works against intuition. For a K-8 count of 100 to 499 the small school district weight is 1.278 plus 0.0003 per student below 500; for 500 to 599 it is 1.158 plus 0.0012 per student below 600 [10]. A 475-ADM school receives $285 less per student than a 300-ADM school, so a lost student takes away about 97% of average revenue, which is why break-even is lower than a flat per-pupil model shows. The weight is not applied individually if the holder contracts with a required management company, shares an identical board with another holder, is a subsidiary of a corporation with other charter-holding subsidiaries, or holds more than one charter, and the combined ADM exceeds 600 [13]. A single-charter holder is therefore a condition of the model.
The Classroom Site Fund, funded by the 0.6-cent education sales tax and part of K-12 state land trust revenues, rose $41 to an estimated $883 per weighted pupil for FY2027, and charter schools' allocations are based on current-year ADM [14], which helps a growing school. Allocations follow Group A weighted student counts [14]; whether that count picks up the small-school weight is to be confirmed, so the model weights the fund at the standard 1.158.
Cash timing is a separate risk. A charter is funded first on an estimated student count based on actual registration, then revised to actual ADM after 40, 100 or 200 days in session, and it must revise its student count, base support level and charter additional assistance before May 15 [13]. A school that opens below its estimate gives money back in the spring of Year 1, when liquidity is thinnest.
Year-by-year revenue ramp (sponsor case)
| Fiscal year | ADM | Group A weight | Base support level | Charter additional assistance | Classroom Site Fund | Federal | Other | Total revenue | Per ADM |
|---|---|---|---|---|---|---|---|---|---|
| FY2029 | 300 | 1.3380 | $2,294,902 | $678,717 | $319,147 | $156,000 | $52,500 | $3,501,267 | $11,671 |
| FY2030 | 360 | 1.3200 | $2,773,095 | $830,750 | $390,636 | $189,072 | $64,260 | $4,247,813 | $11,799 |
| FY2031 | 410 | 1.3050 | $3,186,693 | $965,055 | $453,789 | $217,485 | $74,649 | $4,897,670 | $11,946 |
| FY2032 | 450 | 1.2930 | $3,536,446 | $1,080,391 | $508,022 | $241,090 | $83,570 | $5,449,519 | $12,110 |
| FY2033 | 475 | 1.2855 | $3,786,649 | $1,163,220 | $546,970 | $257,029 | $89,977 | $5,843,847 | $12,303 |
| FY2034 | 475 | 1.2855 | $3,862,382 | $1,186,485 | $557,910 | $259,599 | $91,777 | $5,958,153 | $12,543 |
| FY2035 | 475 | 1.2855 | $3,939,630 | $1,210,215 | $569,068 | $262,195 | $93,612 | $6,074,720 | $12,789 |
| FY2036 | 475 | 1.2855 | $4,018,422 | $1,234,419 | $580,449 | $264,817 | $95,484 | $6,193,593 | $13,039 |
| FY2037 | 475 | 1.2855 | $4,098,791 | $1,259,107 | $592,058 | $267,466 | $97,394 | $6,314,816 | $13,294 |
| FY2038 | 475 | 1.2855 | $4,180,767 | $1,284,289 | $603,900 | $270,140 | $99,342 | $6,438,438 | $13,555 |
All figures in this table are modelled. The ramp is expressed as ADM rather than grade counts because the formula pays one K-8 rate.
Operating expense structure at stabilization (FY2033, 475 ADM)
| Expense | Amount | Share of revenue | Per ADM | Driver |
|---|---|---|---|---|
| Instruction: 21 classroom teachers, 6 SPED/intervention teachers, 6 aides, with benefits | $2,591,201 | 44.3% | $5,455 | Ratios; FY2033 average teacher salary $68,436 |
| Administration and student services | $728,517 | 12.5% | $1,534 | Principal, assistant principal, operations manager, three office staff, counselor, health aide |
| Contracted business services, audit, legal (2.5% of revenue) | $146,096 | 2.5% | $308 | An audit under 2 CFR part 200 is required for an applicant expending $1 million or more of federal assistance in a year [3] |
| Curriculum, supplies, assessment, technology | $199,238 | 3.4% | $419 | $380 per student in FY2029, 2.5% growth |
| Federal program spending (pass-through) | $257,029 | 4.4% | $541 | Equals federal revenue |
| Transportation (limited routes) | $80,193 | 1.4% | $169 | Rural distances |
| Other general and enrollment marketing | $78,647 | 1.3% | $166 | |
| Facility O&M | $337,653 | 5.8% | $711 | $7.50/sq ft in FY2029 |
| Property and liability insurance | $58,493 | 1.0% | $123 | |
| Capital replacement reserve | $32,473 | 0.6% | $68 | |
| Total operating expenses | $4,509,539 | 77.2% | $9,494 | |
| Net operating income | $1,334,308 | 22.8% | $2,809 | |
| Debt service | $1,026,635 | 17.6% | $2,161 |
All figures in this table are modelled. Two ratios carry the credit. Instruction at 44.3% of revenue is below the 52.1% instructional spending percentage Arizona districts reported for FY2025 [12], but the two measures are not built the same way: a charter carries its building debt inside operating revenue. The facility cost share (debt service, O&M, insurance and replacement reserve) is 24.9% of revenue. Lenders and authorizers watch it closely because it cannot flex when enrollment falls, and a quarter of revenue is at the heavy end for a school this size.
Expense growth is set at or above funding growth (salaries 2.5%, O&M 3%, insurance 4%, against 2.0% funding inflation), so stabilized DSCR barely rises (1.30x to 1.31x) as the loan amortizes. Assuming expenses grow with revenue would show improving coverage that the statutory 2% inflation adjustment does not support.
Ten-year pro forma (sponsor ramp)
| Fiscal year | ADM | Revenue | Instruction | Admin and student services | Other operating | Facility O&M, insurance, reserve | Total operating expenses | NOI | Debt service | Capitalized interest applied | Reserve deposit | Cash flow after debt service |
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| FY2029 | 300 | $3,501,267 | $1,565,000 | $486,250 | $447,532 | $380,000 | $2,878,782 | $622,485 | $804,645 | $804,645 | $0 | $622,485 |
| FY2030 | 360 | $4,247,813 | $1,806,562 | $620,125 | $546,457 | $391,600 | $3,364,745 | $883,068 | $804,645 | $0 | $0 | $78,424 |
| FY2031 | 410 | $4,897,670 | $2,140,648 | $693,412 | $633,473 | $403,562 | $3,871,096 | $1,026,574 | $1,026,635 | $0 | $102,663 | -$102,724 |
| FY2032 | 450 | $5,449,519 | $2,361,083 | $710,748 | $707,926 | $415,898 | $4,195,654 | $1,253,865 | $1,026,635 | $0 | $102,663 | $124,567 |
| FY2033 | 475 | $5,843,847 | $2,591,201 | $728,517 | $761,203 | $428,619 | $4,509,539 | $1,334,308 | $1,026,635 | $0 | $102,663 | $205,010 |
| FY2034 | 475 | $5,958,153 | $2,655,981 | $746,729 | $775,984 | $441,737 | $4,620,431 | $1,337,722 | $1,026,635 | $0 | $102,663 | $208,424 |
| FY2035 | 475 | $6,074,720 | $2,722,380 | $765,398 | $791,093 | $455,267 | $4,734,137 | $1,340,583 | $1,026,635 | $0 | $102,663 | $211,285 |
| FY2036 | 475 | $6,193,593 | $2,790,440 | $784,533 | $806,537 | $469,219 | $4,850,729 | $1,342,864 | $1,026,635 | $0 | $102,663 | $213,565 |
| FY2037 | 475 | $6,314,816 | $2,860,201 | $804,146 | $822,326 | $483,609 | $4,970,282 | $1,344,534 | $1,026,635 | $0 | $102,663 | $215,236 |
| FY2038 | 475 | $6,438,438 | $2,931,706 | $824,250 | $838,468 | $498,450 | $5,092,873 | $1,345,565 | $1,026,635 | $0 | $102,663 | $216,267 |
| 10-year total | $54,919,837 | $24,425,202 | $7,164,107 | $7,130,998 | $4,367,961 | $43,088,268 | $11,831,569 | $9,822,367 | $804,645 | $821,308 | $1,992,539 |
All figures in the pro forma are modelled. Cash flow after debt service equals NOI minus debt service, plus capitalized interest applied, minus the reserve deposit. "Other operating" combines contracted services, curriculum, federal pass-through, transportation and general costs.
This is the sponsor's best case. Year 1 shows a surplus only because the loan pays its own first-year interest. FY2031, the first P&I year, covers debt service exactly and goes negative after the reserve deposit. Ten-year cash accumulation averages $199,000 a year against $1.03 million of annual debt service: a thin margin under a 15-year charter.
Debt structure under the CF program
| Term | Modelled structure | Basis |
|---|---|---|
| Lender and program | USDA RD Community Facilities direct loan | 7 CFR part 1942 subpart A [3] |
| Amount | $16,939,893 (89.9% of cost) | Eligible purposes include interest until self-supporting (up to 3 years) and initial operating expenses (ordinarily up to 1 year) [3] |
| Rate | 4.75% fixed (assumption, market tier) | Poverty line rate capped at 5%; intermediate rate at the poverty rate plus half the gap to market, capped at 7%; market rate set using the Bond Buyer Index as guidance [3] |
| Term | 35 years | Not to exceed useful life, State statute or 40 years [3] |
| Repayment | Interest-only FY2029 and FY2030 (FY2029 capitalized); level P&I $1,026,635 from FY2031 over 33 years | Payment factor 6.06% of principal (model) |
| Reserve | 1/10 of one annual installment ($102,663) each year until one installment ($1,026,635) is held | Reserve of at least one average installment, accumulated at no less than one-tenth a year [3] |
| Security | First deed of trust on land and building; assignment of charter school revenue to the extent permitted | Best security position practicable; for a borrower without taxing power, an assignment of assured income or liens with an assignment of income; National Office concurrence if the applicant has existed less than five years [3] |
| Interim financing | Commercial construction loan, prime + 0.50%, repaid at CF closing | Required for loans over $50,000 where available at reasonable rates [3] |
| Covenants | Adequate revenues, insurance and fidelity bonds, annual GAAP financial statements, no added borrowing for the facility without consent | Borrower agreements and reporting [3] |
| Credit elsewhere | Sponsor must certify it cannot finance on reasonable terms | Credit-elsewhere test [3] |
| Equity injection | $1,900,000 (10.1%), deposited by loan closing or start of construction | Applicant contributions go into the construction account first [3] |
The credit-elsewhere test is likely to be met: a start-up charter with no operating history has no rating and no record for a bank to lend against, which is the model's view rather than a sourced fact. The rate still matters at the margin. Each 100 basis points on $16.9 million is about $169,000 a year of interest (computed), and the 10-year Treasury yield was 4.88% on November 9, 2026 [9]. That is why CF suits rural charters, and why the National Office concurrence the rule requires for an applicant under five years old [3] should be planned into the schedule.
The in-program alternative, a CF guaranteed loan, carries a 1.25% guarantee fee, a 0.50% periodic retention fee and an 80% guarantee for FY2026 [15]. At a commercial rate it would raise debt service without fixing the enrollment problem, so it is not modelled.
Debt service schedule
| Fiscal year | Interest | Principal | Total debt service | Ending loan balance | Reserve balance |
|---|---|---|---|---|---|
| FY2029 | $804,645 | $0 | $804,645 | $16,939,893 | $0 |
| FY2030 | $804,645 | $0 | $804,645 | $16,939,893 | $0 |
| FY2031 | $804,645 | $221,990 | $1,026,635 | $16,717,903 | $102,663 |
| FY2032 | $794,100 | $232,534 | $1,026,635 | $16,485,369 | $205,327 |
| FY2033 | $783,055 | $243,580 | $1,026,635 | $16,241,789 | $307,990 |
| FY2034 | $771,485 | $255,150 | $1,026,635 | $15,986,640 | $410,654 |
| FY2035 | $759,365 | $267,269 | $1,026,635 | $15,719,370 | $513,317 |
| FY2036 | $746,670 | $279,965 | $1,026,635 | $15,439,406 | $615,981 |
| FY2037 | $733,372 | $293,263 | $1,026,635 | $15,146,143 | $718,644 |
| FY2038 | $719,442 | $307,193 | $1,026,635 | $14,838,950 | $821,308 |
All figures in this table are modelled. By FY2038, ten years in and five years before a 15-year charter starting in FY2029 would end, the loan has amortized only 12.4%. If the charter were not renewed at year 15, the lender would hold a special-use school building against a balance of roughly $13.1 million at the end of FY2043.
Debt service coverage and break-even
DSCR by year
| Fiscal year | Sponsor ramp DSCR | Cumulative cash (sponsor) | Days cash on hand | CF reserve balance | Conservative-case DSCR (320 ADM) |
|---|---|---|---|---|---|
| FY2029 | 0.77x (interest capitalized) | $622,485 | 79 | $0 | 0.18x (interest capitalized) |
| FY2030 | 1.10x | $700,909 | 76 | $0 | 0.47x |
| FY2031 | 1.00x | $598,185 | 56 | $102,663 | 0.51x |
| FY2032 | 1.22x | $722,752 | 63 | $205,327 | 0.60x |
| FY2033 | 1.30x | $927,762 | 75 | $307,990 | 0.80x |
| FY2034 | 1.30x | $1,136,186 | 90 | $410,654 | 0.79x |
| FY2035 | 1.31x | $1,347,471 | 104 | $513,317 | 0.79x |
| FY2036 | 1.31x | $1,561,036 | 117 | $615,981 | 0.79x |
| FY2037 | 1.31x | $1,776,272 | 130 | $718,644 | 0.79x |
| FY2038 | 1.31x | $1,992,539 | 143 | $821,308 | 0.79x |
All figures in this table are modelled. DSCR is NOI divided by scheduled debt service. In FY2029 the debt service is paid from capitalized interest, so the ratio shows operating strength only. Days cash on hand is cumulative operating cash divided by daily operating expense and excludes the CF reserve.
The model treats 1.20x stabilized coverage with at least 45 days cash on hand as the practical floor for a lender; that is an assumption, not a program rule. The sponsor case clears it from FY2032 with thin liquidity; the conservative case never covers debt service. The authorizer measures financial performance too: a sponsor reviews a charter at five-year intervals using a performance framework and may revoke it if the holder fails to meet the framework's financial performance expectations [5]. The Board's current coverage and liquidity measures are a diligence item. A 1.00x third year would draw authorizer attention just as the lender's covenant is tested.
Break-even
| Coverage target | Required stabilized ADM | Share of 500-seat capacity | Required headcount as a share of 2,471 trade-area K-8 students |
|---|---|---|---|
| 1.00x | 410 | 82.0% | 17.5% |
| 1.10x | 429 | 85.7% | 18.3% |
| 1.20x | 456 | 91.2% | 19.4% |
| 1.25x | 470 | 93.9% | 20.0% |
ADM figures are model results; shares use headcount at a 95% ADM ratio against the ACS count [4]. Measured at FY2034 (stabilized, sponsor case), revenue could fall 5.2% with expenses unchanged before coverage hits 1.00x; expenses could rise 6.7% with revenue unchanged. Those are narrow cushions for a school whose revenue is set annually by the legislature and whose enrollment is untested.
Returns
A nonprofit charter holder does not distribute profit, so IRR is a notional measure here. It is still useful to a lender because it shows whether the real estate, valued on its income, recovers the capital put into it.
| Measure | Value |
|---|---|
| Total project cost (Year 0) | $18,839,893 |
| Equity (Year 0) | $1,900,000 |
| FY2039 NOI (exit-year forward NOI) | $1,345,925 |
| Exit cap rate (assumption) | 8.0% |
| Exit value at end of FY2038 | $16,824,057 |
| Loan balance at exit | $14,838,950 |
| CF reserve released at exit | $821,308 |
| Unlevered IRR (10 years) | 5.3% |
| Levered IRR (10 years) | 13.6% |
| Equity multiple | 2.53x |
| Payback of equity from operating cash flow | 10 years (cumulative $1,992,539 against $1,900,000) |
All figures in this table are modelled. The unlevered return of 5.3% barely clears the 4.75% loan rate, and the income value is $2.0 million below cost, so loan-to-value at completion is about 100%. A vacant K-8 building in a town of 8,300 would realise less still in a default. The levered IRR is high only because equity is small; it measures the subsidy in a 4.75% 35-year loan, not project strength.
Sensitivity and stress tests
Two-way grid: FY2034 DSCR by CF rate and stabilized ADM
Each cell uses the sponsor ramp to FY2032 (300, 360, 410, 450 ADM) and then holds the stated ADM from FY2033.
| Stabilized ADM | 4.25% | 4.75% | 5.25% | 5.75% | 6.25% |
|---|---|---|---|---|---|
| 300 | 0.63x | 0.59x | 0.55x | 0.52x | 0.48x |
| 350 | 0.81x | 0.75x | 0.71x | 0.66x | 0.62x |
| 400 | 1.01x | 0.95x | 0.89x | 0.83x | 0.78x |
| 425 | 1.14x | 1.06x | 1.00x | 0.93x | 0.88x |
| 450 | 1.31x | 1.23x | 1.15x | 1.08x | 1.01x |
| 475 | 1.40x | 1.30x | 1.22x | 1.14x | 1.07x |
| 500 | 1.52x | 1.42x | 1.32x | 1.24x | 1.17x |
All figures in this table are modelled. Enrollment dominates. Moving 50 students changes coverage by about 0.15x to 0.30x; moving the rate 50 basis points changes it by about 0.08x. The CF rate matters to affordability, but the file is decided by the enrollment row.
Downside scenarios (500-seat building)
| Scenario | CF loan | Minimum DSCR FY2031 to FY2038 | FY2033 DSCR | FY2038 DSCR | 10-year cumulative cash after debt service |
|---|---|---|---|---|---|
| Base (sponsor ramp) | $16,939,893 | 1.00x | 1.30x | 1.31x | $1,992,539 |
| A. Conservative enrollment (to 320 ADM) | $16,939,893 | 0.51x | 0.80x | 0.79x | -$3,301,948 |
| B. Funding freeze, no inflation FY2030 to FY2032 | $16,939,893 | 0.83x | 1.00x | 0.98x | -$496,352 |
| C. Hard-cost overrun +12%, funded by a larger loan | $18,944,974 | 0.89x | 1.16x | 1.17x | $827,948 |
| D. Staff pay reset +7% from FY2031 | $16,939,893 | 0.85x | 1.12x | 1.11x | $518,784 |
| E. Retention shortfall, enrollment 10% below plan from FY2031 | $16,939,893 | 0.79x | 1.09x | 1.09x | $186,666 |
| F. CF rate 100 bp higher at closing (5.75%) | $17,127,983 | 0.88x | 1.14x | 1.15x | $553,244 |
| G. A and B combined | $16,939,893 | 0.40x | 0.59x | 0.56x | -$5,014,272 |
All figures in this table are modelled. Each scenario is plausible. B tests the statutory adjustment, which funds the lesser of 2% or the GDP price deflator [6]. D reflects a labour market where the statewide average district teacher salary rose only about 1% in FY2025 [12], which can reverse through legislative pay initiatives. E is the risk of families trying a new school for a year and returning to the district. Every downside takes the minimum DSCR below 0.90x, and none requires anything unusual.
What the evidence supports: a resized first phase
The model also sizes a building to the conservative case: 320 ADM, 26,400 sq ft (330-seat design), identical unit costs, on the same 10-acre site so a second phase can follow demonstrated demand.
| Measure | Phase 1, 330-seat design |
|---|---|
| Total project cost | $13,226,885 |
| CF direct loan | $11,326,885 |
| Equity | $1,900,000 (14.4%) |
| Annual P&I from FY2031 | $686,461 |
| DSCR FY2029 / FY2030 / FY2031 / FY2032 | 0.51x (interest capitalized) / 0.96x / 0.97x / 1.10x |
| DSCR FY2033 to FY2038 | 1.40x to 1.42x |
| Break-even ADM at 1.00x / 1.20x | 286 / 307 |
| Enrollment 15% lower (to 270 ADM) | 1.01x stabilized |
| Funding freeze FY2030 to FY2032 | 1.09x stabilized |
| Lowest days cash on hand | 19 days (FY2032) |
| Unlevered / levered IRR | 5.2% / 9.9% |
All figures in this table are modelled. Phase 1 is tight in its ramp years and its liquidity dips below 20 days in FY2032, but it stabilizes at 1.40x on enrollment equal to about 13.6% of the trade area's K-8 students, survives a 15% enrollment miss or a three-year funding freeze, and holds debt service to 16.7% of revenue (facility share 23.8%).
Program compliance checklist
| Requirement | Rule | Status in the model |
|---|---|---|
| Eligible applicant | Public body, not-for-profit organization or federally recognized tribe [3] | Nonprofit charter holder; confirm IRS status and Arizona corporate standing |
| Rural location | No loans to a city or town over 20,000 by the most recent decennial census [3] | Wickenburg estimates base 7,514 and 2025 estimate 8,305 [1]; confirm decennial count |
| Primarily serves rural areas | Essential community facilities must primarily serve rural areas [3] | Trade area of six ZCTAs outside the Phoenix urban areas; confirm Wittmann's rural status |
| Public use | All facilities financed under the subpart must be for public use [3] | Tuition-free, open-enrollment public charter school; charters may not charge tuition to Arizona residents [13] |
| Credit elsewhere | Applicant certifies inability to finance from own resources or commercial credit at reasonable rates and terms; RD documents [3] | To be documented with commercial lender responses |
| Legal authority | Authority to construct, operate and maintain the facility and to give security for and repay the loan [3] | Charter contract and board resolutions; charter term 15 years, renewable for 20 [5] |
| Economic feasibility | Revenues sufficient for operation, maintenance, a reasonable reserve and debt payment [3] | Met only in the sponsor ramp; not met in the conservative case; met in Phase 1 |
| Rate tier | Poverty, intermediate or market by service-area income and purpose [3] | Market tier assumed; poverty tier unavailable (not a health or sanitary project) |
| Term | Not over useful life, State statute or 40 years [3] | 35 years modelled |
| Reserve | At least one average installment, built at one-tenth a year [3] | $102,663 a year to $1,026,635 |
| Security | Best practicable position; National Office concurrence for an applicant under five years old [3] | Deed of trust plus revenue assignment; concurrence needed |
| Interim financing | Commercial interim financing for loans over $50,000 where available [3] | Construction loan to CF takeout |
| Environmental review | 7 CFR part 1970 [3] | Required before commitment |
| Civil rights | Title VI applies to borrowers; Title IX to education programs receiving Agency assistance [3] | Open-enrollment charter; nondiscrimination policies |
| Audit and reporting | Annual GAAP statements; 2 CFR part 200 audit at $1 million or more of federal expenditure; quarterly reports in the first full year for new borrowers [3] | Budgeted in contracted services |
| State zoning treatment | Charter treated as a district school for zoning and fees; determinations within 30 or 90 days [7] | Favourable |
| Charter siting limit | A State Board-sponsored charter may not be on school district property unless the district governing board grants this authority [5] | Site to be privately acquired |
| Funding statute | Charter base support level and additional assistance [13]; base level [11]; weights [10] | Modelled at FY2027 statute plus 2% a year |
Risks and mitigants
| Risk | Why it matters to the credit | Mitigant a lender would look for |
|---|---|---|
| Enrollment base | The town has 754 residents under 18 [4]; 500 seats need about 20% of all K-8 students across six ZIP areas (computed) | Resize to Phase 1; require signed intent-to-enroll forms covering at least 80% of Year 1 ADM before closing |
| Retention after Year 1 | Families who try a new school may return to the district school | Grade-by-grade ramp; covenant to report October and 100-day counts to the lender |
| ESA competition | 102,891 ESA enrollees in FY2026; about 59% of new FY2026 enrollees came from public schools [6] | Programme differentiation; capture rates set below the statewide charter share |
| Funding inflation | Base level and charter additional assistance rise by the lesser of 2% or the deflator [6] | Stress test B; expense growth set above funding growth in the base case |
| First-year count true-up | Initial funding on estimated registration; counts revised before May 15 [13] | Conservative Year 1 estimate; liquidity reserve |
| Charter non-renewal or revocation | 15-year term; reviews at five-year intervals; revocation for a breach of the charter or for failing the framework's academic, operational or financial expectations [5] | Renewal covenant; amortization front-loaded where cash allows; RD consent on charter amendments |
| Small-school weight eligibility | Lost if the holder's combined group exceeds 600 ADM under the statute's conditions [13] | Covenant to keep a single-charter structure, or a new credit review |
| Teacher labour market | Statewide average district teacher salary rose only about 1% in FY2025 [12] | Stress test D; budget teacher pay near the district scale |
| Construction cost | A 12% overrun raises the loan to $18.9M and cuts stabilized DSCR to 1.16x (model) | Guaranteed maximum price contract; 6% hard contingency; sponsor overrun commitment |
| Collateral value | Income value of $16.8M is below cost; special-use asset in a small town (model) | Accept the CF loan as a cash-flow credit; larger equity; full building and site appraisal |
| Interest rate at closing | 100 bp higher rate cuts stabilized DSCR from 1.30x to 1.14x (model) | Confirm the quarterly CF rate at approval; size debt at a stressed rate |
| Utilities and site | Off-site extensions can exceed allowance | Site due diligence before land purchase; utility will-serve letters |
| Liquidity in ramp years | Phase 1 falls to 19 days cash in FY2032 (model) | Sponsor-funded ramp reserve of about $250,000 held to FY2033 |
Model determination
As structured, the modelled project is not financeable. The building's arithmetic is defensible: an $18.8 million campus close to the state's district-school formula in cost [8], at an assumed 4.75% CF rate, reaches 1.30x at 475 students. The students are the problem. Wickenburg's median age is 65.2 against 37.6 for the county; the district area has about 1,316 residents enrolled in kindergarten through grade 8 and the six-ZIP trade area about 2,471 [4]. Reaching 475 ADM takes about 20% of all of them, the statewide charter share, in a town the model assumes has no charter school; break-even takes 17.5%. The model's ring capture rates, already generous for a new school, give about 426 ADM and about 1.06x, and the conservative case of 320 ADM covers 0.80x with a $3.3 million ten-year cash deficit. No reserve or rate structure fixes that.
The same site and program support a smaller first phase. A 330-seat building with an $11.3 million CF loan reaches 1.40x at 320 ADM, breaks even at 286 ADM, and holds about 1.0x under a 15% enrollment miss or a three-year funding freeze. That version is financeable under 7 CFR part 1942 subpart A, subject to conditions a lender would likely set:
- Charter in hand. An executed charter contract with the Arizona State Board for Charter Schools, with a stated term and first fiscal year, before RD obligates funds.
- Enrollment evidence. Signed intent-to-enroll forms for at least 80% of Year 1 ADM (160 of 200), with home ZIP codes that confirm the trade-area mix, before construction starts.
- Single-charter covenant. The holder keeps one charter and no management-company, common-board or subsidiary arrangement that would remove the small-school weight [13].
- Ramp reserve. About $250,000 of sponsor cash held until FY2033 or two consecutive years at 1.20x, on top of the CF reserve.
- Coverage and liquidity covenants. A 1.10x DSCR test from FY2031 and 45 days cash on hand from FY2033, with a consultant-review trigger below either.
- Count reporting. October enrollment and 40-, 100- and 200-day ADM reports to the lender, and prompt notice of any authorizer intervention or notice of intent to revoke.
- Phase 2 gate. Expansion to 500 seats only after two consecutive years at 95% of Phase 1 capacity with a waitlist, sized at that time on actual retention.
- Cost certainty. A guaranteed maximum price construction contract within 5% of budget, and a sponsor commitment to fund overruns.
- Rate and tier confirmation. The CF rate tier and quarterly rate confirmed at approval, with debt re-sized if the rate exceeds 5.25%, and National Office concurrence for a new applicant obtained [3].
With those conditions, the credit becomes what CF lending is meant to finance: an essential public facility, sized to the rural community it serves, with growth earned rather than assumed.
Frequently Asked Questions
- Can a charter school borrow from the USDA Community Facilities program?
- Yes, if the borrower is a public body or a not-for-profit organization, the facility is not in a city or town of more than 20,000 people in the latest decennial census, and it primarily serves rural areas. A tuition-free public charter school operated by a nonprofit charter holder is a public-use facility under 7 CFR 1942.17. The borrower must also certify that it cannot get credit elsewhere on reasonable terms, and an applicant in existence for less than five years needs National Office concurrence on its security.
- Why was Wickenburg chosen over Gila Bend?
- Both towns are under 20,000 and outside the Phoenix urban area, so both pass the CF location test. Gila Bend's 2025 estimate is 1,816 and falling, which cannot support a K-8 school of any meaningful size. Wickenburg is about 8,300 and growing, has its own small urban area, and sits at the centre of a trade area of six ZIP codes. Even so, 500 seats would need about 20% of every K-8 student in that area, so the model recommends a smaller first phase.
- How is an Arizona charter school funded per student?
- The state pays a base support level (the statutory base level times grade and special-population weights), plus charter additional assistance, as a single amount based on average daily membership, and the Classroom Site Fund adds a per-pupil amount. For FY2027 the K-8 charter additional assistance is $2,174.54 and the Classroom Site Fund estimate is $883 per weighted pupil. The statutory base level for fiscal year 2026-2027 is $5,215.53. In this model a 475-student school receives about $11,386 per student in FY2029, including modest federal and local revenue.
- What is the small-school weight and why does it matter here?
- Arizona raises the K-8 funding weight for small student counts below 600, and a holder of one charter qualifies. At 300 students the weight is 1.338; at 475 it is 1.2855; the standard K-8 weight is 1.158. A smaller school therefore receives more per student. This cushions an enrollment shortfall and lowers break-even, but the weight is lost if the charter holder is part of an affiliated group with combined membership above 600.
- What DSCR does this model treat as financeable?
- The model treats 1.20x stabilized coverage, with at least 45 days cash on hand, as the practical floor for a lender; that is an assumption, not a program rule. The 500-seat plan reaches 1.30x only if it fills to 475 students, and at 320 students it covers 0.80x. The resized 330-seat phase reaches 1.40x at 320 students.
- How does the charter term affect a 35-year loan?
- An Arizona charter lasts 15 years and can be renewed for 20-year periods, with reviews at five-year intervals. A loan longer than the charter depends on renewal. Lenders handle that with covenants on authorizer standing, reporting of any intervention, and amortization that reduces the balance before the renewal decision. In this model the loan has amortized only 12.4% after ten years.
- What CF interest rate applies to a school in Wickenburg?
- CF direct loans have three tiers. The poverty line rate needs a low-income service area and, for a project that is not a health care facility, a primary purpose of meeting health or sanitary standards, so it is unavailable for a new school. The intermediate rate needs service-area income at or below the State nonmetropolitan median. This model assumes the market tier at 4.75%, pending confirmation of the income test and the quarterly rate in force at approval.
- What would make the 500-seat version financeable?
- Evidence that the students exist. The building needs about 410 students in average daily membership to break even and 456 for 1.20x coverage, which means enrolling about 17.5% to 19.4% of every K-8 student in the six ZIP areas. A lender would want two years of operating history at or near Phase 1 capacity, with a waitlist and confirmed retention, before financing the full building. Phasing on the same 10-acre site keeps that option open.
Sources
- 1.U.S. Census Bureau. "Annual Estimates of the Resident Population for Incorporated Places and Minor Civil Divisions: April 1, 2020 to July 1, 2025, Arizona" (Vintage 2025, sub-est2025_4.csv). https://www2.census.gov/programs-surveys/popest/datasets/2020-2025/cities/totals/sub-est2025_4.csv (accessed 2026-11-11)
- 2.U.S. Census Bureau. "2020 Census Urban Areas" list (2020_Census_ua_list_all.xlsx). https://www2.census.gov/geo/docs/reference/ua/2020_Census_ua_list_all.xlsx (accessed 2026-11-11)
- 3.U.S. Government Publishing Office, GovInfo. Code of Federal Regulations, Title 7, Part 1942, Subpart A, Community Facility Loans (revised as of January 1, 2025). https://www.govinfo.gov/content/pkg/CFR-2025-title7-vol13/xml/CFR-2025-title7-vol13-part1942.xml (accessed 2026-11-11)
- 4.U.S. Census Bureau. American Community Survey 2020 to 2024 5-year table-based summary file, tables B01003, B01002, B09001, B09020, B14001, B19013 and B25010. https://www2.census.gov/programs-surveys/acs/summary_file/2024/table-based-SF/data/5YRData/ (accessed 2026-11-11)
- 5.Arizona State Legislature. Arizona Revised Statutes § 15-183, charter schools. https://www.azleg.gov/ars/15/00183.htm (accessed 2026-11-11)
- 6.Arizona Joint Legislative Budget Committee. "FY 2027 Appropriations Report: Department of Education." https://www.azjlbc.gov/27AR/ade.pdf (accessed 2026-11-11)
- 7.Arizona State Legislature. Arizona Revised Statutes § 15-189.01, charter schools; zoning. https://www.azleg.gov/ars/15/00189-01.htm (accessed 2026-11-11)
- 8.Arizona Joint Legislative Budget Committee. "FY 2027 Appropriations Report: ADOA School Facilities Division." https://www.azjlbc.gov/27AR/doa-sfd.pdf (accessed 2026-11-11)
- 9.Board of Governors of the Federal Reserve System. "H.15 Selected Interest Rates (Daily)," release of November 10, 2026. https://www.federalreserve.gov/releases/h15/ (accessed 2026-11-11)
- 10.Arizona State Legislature. Arizona Revised Statutes § 15-943, Base support level. https://www.azleg.gov/ars/15/00943.htm (accessed 2026-11-11)
- 11.Arizona State Legislature. Arizona Revised Statutes § 15-901, Definitions. https://www.azleg.gov/ars/15/00901.htm (accessed 2026-11-11)
- 12.Arizona Auditor General. "Arizona School District Spending Analysis and Data File, Fiscal Year 2025" (February 26, 2026). https://www.azauditor.gov/arizona-school-district-spending-analysis-and-data-file-fiscal-year-2025 (accessed 2026-11-11)
- 13.Arizona State Legislature. Arizona Revised Statutes § 15-185, Charter schools; financing; civil penalties; transportation; definition. https://www.azleg.gov/ars/15/00185.htm (accessed 2026-11-11)
- 14.Arizona Joint Legislative Budget Committee. "Estimated Classroom Site Fund Per Pupil Amount for FY 2027." https://www.azjlbc.gov/units/csf-fy2027033026.pdf (accessed 2026-11-11)
- 15.U.S. Department of Agriculture, Rural Development. "OneRD Annual Notice of Guarantee Fee Rates, Periodic Retention Fee Rates, Loan Guarantee Percentage and Fee for Issuance of the Loan Note Guarantee Prior to Construction Completion for Fiscal Year 2026," 91 FR 11272 (March 9, 2026), GovInfo copy. https://www.govinfo.gov/content/pkg/FR-2026-03-09/html/2026-04581.htm (accessed 2026-11-11)
Related
- Rural Health Clinic in Greenbrier, Faulkner County, Arkansas: A USDA Community Facilities Direct Loan Model Study
- What is a bankable feasibility study?
- Bankable feasibility study framework
- Charter School feasibility study
- Daycare feasibility study
- Mixed-Use feasibility study
- Retail feasibility study
- Medical Office feasibility study
- Multifamily feasibility study